Add phased implementation roadmap
This commit is contained in:
@@ -0,0 +1,294 @@
|
|||||||
|
# Implementation Roadmap
|
||||||
|
|
||||||
|
## Purpose
|
||||||
|
|
||||||
|
This document defines the planned implementation order for the Xterra Overland Power & Monitoring Dashboard.
|
||||||
|
|
||||||
|
The goal is to build the system incrementally, validating hardware and software at each stage before adding additional complexity.
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Current Status
|
||||||
|
|
||||||
|
## Complete
|
||||||
|
|
||||||
|
* Project architecture defined
|
||||||
|
* Hardware architecture defined
|
||||||
|
* UART protocol defined
|
||||||
|
* Pico architecture defined
|
||||||
|
* UI wireframes defined
|
||||||
|
* ESP32 firmware compiles
|
||||||
|
* Simulator exists and functions
|
||||||
|
|
||||||
|
## In Progress
|
||||||
|
|
||||||
|
* ESP32 controller firmware
|
||||||
|
* Communication protocol implementation
|
||||||
|
|
||||||
|
## Not Started
|
||||||
|
|
||||||
|
* Pico firmware
|
||||||
|
* Display integration
|
||||||
|
* Touch integration
|
||||||
|
* Buzzer integration
|
||||||
|
* End-to-end communications
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 1: ESP32 Hardware Bring-Up
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Verify cargo-controller hardware.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* Flash ESP32 firmware
|
||||||
|
* Verify boot process
|
||||||
|
* Verify AP mode
|
||||||
|
* Verify HTTP API
|
||||||
|
* Verify relay outputs
|
||||||
|
* Verify DS18B20 framework
|
||||||
|
* Verify UART initialization
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* ESP32 boots reliably
|
||||||
|
* Relay outputs function correctly
|
||||||
|
* Status API responds correctly
|
||||||
|
* No crashes or watchdog resets
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 2: Pico Hardware Bring-Up
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Verify dashboard hardware.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* Verify Pico 2 W operation
|
||||||
|
* Verify ST7796S display
|
||||||
|
* Verify FT6336U touch controller
|
||||||
|
* Verify buzzer operation
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* Display initializes reliably
|
||||||
|
* Touch events are detected
|
||||||
|
* Buzzer can be activated
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 3: UART Communications
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Establish communications between Pico and ESP32.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* Wire UART over CAT5
|
||||||
|
* Implement status requests
|
||||||
|
* Implement status responses
|
||||||
|
* Implement relay commands
|
||||||
|
* Implement error handling
|
||||||
|
* Implement communication timeout detection
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* Pico receives live status
|
||||||
|
* Pico can control relays
|
||||||
|
* Communication loss is detected
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 4: Dashboard UI Foundation
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Render live data on the touchscreen.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* Create screen manager
|
||||||
|
* Create app state
|
||||||
|
* Create dashboard screen
|
||||||
|
* Create navigation bar
|
||||||
|
* Create communication status indicators
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* Live battery data displayed
|
||||||
|
* Live temperature data displayed
|
||||||
|
* Navigation functional
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 5: Detailed Screens
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Implement all planned screens.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
### Battery Screen
|
||||||
|
|
||||||
|
* SOC
|
||||||
|
* Voltage
|
||||||
|
* Current
|
||||||
|
* Runtime
|
||||||
|
* Temperature
|
||||||
|
|
||||||
|
### Temperature Screen
|
||||||
|
|
||||||
|
* Fridge Zone 1
|
||||||
|
* Fridge Zone 2
|
||||||
|
* Rear Seat
|
||||||
|
* Outside Air
|
||||||
|
|
||||||
|
### Power Screen
|
||||||
|
|
||||||
|
* Starlink control
|
||||||
|
* Fridge control
|
||||||
|
|
||||||
|
### System Screen
|
||||||
|
|
||||||
|
* Communication status
|
||||||
|
* Sensor status
|
||||||
|
* Firmware information
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* All screens functional
|
||||||
|
* Navigation stable
|
||||||
|
* Live updates working
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 6: Alarm System
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Implement alerting and warning system.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* Alarm manager
|
||||||
|
* Alarm overlay
|
||||||
|
* Communication alarms
|
||||||
|
* Battery alarms
|
||||||
|
* Temperature alarms
|
||||||
|
* Sensor fault alarms
|
||||||
|
* Buzzer manager
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* Alarms trigger correctly
|
||||||
|
* Alarm overlay displays correctly
|
||||||
|
* Buzzer alerts function correctly
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 7: DS18B20 Integration
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Implement all production sensors.
|
||||||
|
|
||||||
|
## Sensors
|
||||||
|
|
||||||
|
### Fridge Zone 1
|
||||||
|
|
||||||
|
Monitor refrigerator compartment.
|
||||||
|
|
||||||
|
### Fridge Zone 2
|
||||||
|
|
||||||
|
Monitor freezer compartment.
|
||||||
|
|
||||||
|
### Rear Seat Area
|
||||||
|
|
||||||
|
Monitor passenger compartment.
|
||||||
|
|
||||||
|
### Outside Air
|
||||||
|
|
||||||
|
Monitor ambient exterior temperature.
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* All sensors report correctly
|
||||||
|
* Sensor failures are detected
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 8: JBD/Xiaoxiang BMS Integration
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Replace simulated battery data with live battery data.
|
||||||
|
|
||||||
|
## Tasks
|
||||||
|
|
||||||
|
* BLE communication
|
||||||
|
* Battery status retrieval
|
||||||
|
* Runtime calculations
|
||||||
|
* Health monitoring
|
||||||
|
|
||||||
|
## Success Criteria
|
||||||
|
|
||||||
|
* Live battery data displayed
|
||||||
|
* No simulated battery values required
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 9: Vehicle Integration
|
||||||
|
|
||||||
|
## Goal
|
||||||
|
|
||||||
|
Add vehicle-specific information.
|
||||||
|
|
||||||
|
## Potential Features
|
||||||
|
|
||||||
|
* Ignition state
|
||||||
|
* OBD-II integration
|
||||||
|
* CAN bus integration
|
||||||
|
* Engine information
|
||||||
|
* Fuel information
|
||||||
|
|
||||||
|
## Status
|
||||||
|
|
||||||
|
Future planning only.
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Milestone 10: Future Expansion
|
||||||
|
|
||||||
|
## Potential Features
|
||||||
|
|
||||||
|
* Additional relays
|
||||||
|
* Inverter control
|
||||||
|
* Lighting control
|
||||||
|
* Starlink diagnostics
|
||||||
|
* GPS integration
|
||||||
|
* Home Assistant integration
|
||||||
|
|
||||||
|
## Status
|
||||||
|
|
||||||
|
Future planning only.
|
||||||
|
|
||||||
|
---
|
||||||
|
|
||||||
|
# Explicitly Not Planned
|
||||||
|
|
||||||
|
The following items are currently out of scope:
|
||||||
|
|
||||||
|
* Cloud connectivity
|
||||||
|
* Internet dependency
|
||||||
|
* User accounts
|
||||||
|
* Persistent logging
|
||||||
|
* Historical graphing
|
||||||
|
* Subscription services
|
||||||
|
|
||||||
|
The system should remain fully functional offline.
|
||||||